RO/RO

We have recently carried out the loading of 3x650mtons boilers and some minor items.

2x22 axles spmt trailers were deployed to move items from producer’s yard to port of loading the boilers and the other special items were loaded onto a 90m ro/ ro barge and laid, lashed secured and welded on grillage we had perviously installed.

Cargo:

Substation section 1
56.30x14.7x8.90m/ 823.3 tons

Substation section 2
24.50x14.7x8.90m/ 422.4 tons

The 824T module was loaded by means of SPMT in 84 axles configuration From Producer’s yard at Ravenna to on- loading pier, to be shipped by RO/RO bage To final destination Tengiz, KZ